10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

These 10 free RPO questions are organized by exam domain, so you can see how each part of the Registered Product Owner blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Core Scrum

Question 1

Two department heads disagree about which feature should come first. After comparing customer impact, dependencies, and effort with stakeholders and Developers, the Product Owner orders the Product Backlog. A steering committee asks the Scrum Master to replace that order with the result of a departmental vote. Which response preserves the relevant Scrum accountabilities?

Show answer & explanation

Correct answer: C - Keep the Product Owner accountable for ordering; use the Scrum Master to help resolve the disagreement.

Question 2

A wholesaler wants to learn whether existing shop-owner customers will place repeat orders without calling a sales representative. Its story map includes finding a previously purchased product, choosing a quantity, submitting the order, and receiving confirmation. Recommendations and additional payment methods are later possibilities. Which first pilot would provide direct evidence of unaided ordering?

Show answer & explanation

Correct answer: A - One usable reorder path covering product selection, quantity, submission, and confirmation for existing account customers.

Question 3

Only one of two independent improvements can be worked on at a time, starting now. A search upgrade takes four weeks and loses $8,000 of value for every week until it is released. An export improvement takes one week and loses $3,000 per week until release. Each is released immediately on completion; work cannot overlap or pause, and implementation costs are unaffected by order. Which sequence minimizes total lost value across both improvements?

Show answer & explanation

Correct answer: B - Export first, then search; total lost value of $43,000.

Question 4

For a conveyor controller, the Definition of Done includes a passed emergency-stop test. Routine operating behaviors meet their acceptance criteria, but the emergency stop fails intermittently. The controller has not been released. Under pressure to finish the Sprint, the Product Owner asks whether the item can count as complete. How should it be treated?

Show answer & explanation

Correct answer: A - Keep it unfinished until the emergency-stop failure is corrected and reverified.

Question 5

After six releases were delayed by the same fragile configuration process, a Product Owner says, 'Customers never ask us to fix that.' There is no current outage. How should a proposed repair compete with feature work?

Show answer & explanation

Correct answer: B - Compare the repair's cost and expected delay reduction with the value of competing product work.

Domain 2: Lean Principles

Question 6

A value-stream map of small product changes shows two hours of analysis, five days waiting after approval, three hours of implementation, and one hour of verification. Approved changes wait because they are forwarded only at a weekly coordination meeting; no control requires that batching. Downstream staff have spare capacity. Where should the first flow-improvement experiment focus?

Show answer & explanation

Correct answer: B - Forward approved changes continuously rather than holding them for the weekly meeting.

Domain 3: Agile Manifesto

Question 7

A deployment checklist prevents recurring setup errors; a status report repeats Product Backlog information that every stakeholder can already see. The report has no other purpose. What treatment fits the Agile Manifesto's view of documentation?

Show answer & explanation

Correct answer: D - Keep the useful checklist and retire the report that duplicates visible information.

Domain 4: Patterns of High Performing Teams

Question 8

Halfway through a Sprint, an unexpected integration problem makes the remaining plan infeasible. The Sprint Goal is still valuable. The team has tried a different implementation approach, but that has not restored feasibility; help from other teams has not yet been explored. In Scrum Inc.'s Scrum Emergency Procedure, which recovery move comes next?

Show answer & explanation

Correct answer: D - Find out whether another capable team can take on part of the remaining work.

Question 9

Every member of a stable team completes the same anonymous role-happiness survey each Sprint. Its scale is 1 = very unhappy, 2 = unhappy, 3 = neither happy nor unhappy, 4 = happy, and 5 = very happy. The mean rises from 3.4 to 4.2 while comparable Done work remains unchanged. Comments describe fewer disruptive handoffs. What can the Product Owner infer from these results?

Show answer & explanation

Correct answer: C - The ratings suggest a better work experience, not a proven increase in delivery capacity.

Domain 5: Scrum@Scale

Question 10

A company adopting Scrum@Scale needs both an organization-wide Product Owner team and a forum where stakeholders and Product Owners align product priorities. Which pairing correctly distinguishes those functions?

Show answer & explanation

Correct answer: D - Executive MetaScrum Team for organization-wide product direction; MetaScrum event for stakeholder priority alignment.